David F GliddenandClaude Opus 5 ef6fa94dcd [FIX] Stamp 16 superseded trackers; harvest the rule one of them carried
The record is updated where information ARRIVES and never where a reader LOOKS.
Three instances found the same day, each with the correct information already
written down elsewhere:

  REVIEWED-81 (AUTHORIZED 07-28)      -> PENDING-81 still reads open
  the ARC open-work register, which   -> those 6 trackers still read live
    says in its own description that
    it supersedes them, with a
    per-file verified verdict
  register entry A2: "the content     -> register entry B3, one page below:
    half (B3) is now unblocked +         "[OPEN - gated on A2]"
    started" (06-17)

The third is the sharpest: both halves sit in the SAME document, so no tooling
gap explains it. ~/CLAUDE.md already rules this under Memory Discipline
("mark the superseded record as superseded"); the rule is being applied to facts
and not to trackers, PENDING items or register entries, which are also facts
about state.

Executed under steward authorization, arrears only:
- 16 trackers stamped `superseded_by:` + `superseded_on:` AND a visible in-body
  banner. The banner is the point — metadata alone repeats the defect, since the
  finding is about what a reader sees. 9 obsoleted by the 2026-07-07 MemPalace
  wind-down; 7 already carrying the register's own verified `DONE-retire`.
- B3's label corrected, with the two-month error left visible rather than
  silently amended.
- Nothing moved, renamed or deleted: 381 pointers resolve, 0 dead, 0 mis-authored.

HARVESTED BEFORE STAMPING, and this is why the harvest came first:
`project-mempalace-library-incremental-remine-strategy` carried a steward-verbatim
rule that is instrument-independent — never run a single multi-day index; order by
criticality; gate each tranche on READBACK, not on write-success (933,576 drawers
once stored successfully and could not be read back at all). It lived only inside
a MemPalace tracker, so retiring the instrument would have retired the rule with
it. ~/CLAUDE.md names that exact hazard: "state the obligation first and the
instrument second, or the next retired tool takes a rule down with it." Now
`feedback-bulk-indexing-runs-incrementally-with-readback.md`, and it applies to
studium-engine corpus work.

Held back deliberately: 2 correctly-parked files with named dependencies, 2 named
nowhere (returned to the steward), and 39 trackers unread — recorded as a gap,
not as a finding.

Measurement note: every earlier estimate of tracker staleness was wrong, because
both mtime and git-last-commit were reset across 283 files by the 2026-06-06
normalization sweep. The honest figure excludes it: median 90 days.

Filed as PENDING-142 ADDENDUM 2 per steward direction (fold, do not file anew).

Co-Authored-By: Claude Opus 5 <noreply@anthropic.com>
Claude-Session: https://claude.ai/code/session_013Y6t6qx7cpaCu5xGdD36u4
2026-08-17 15:23:26 +02:00

75 lines
17 KiB
Markdown
Raw Blame History

This file contains ambiguous Unicode characters
This file contains Unicode characters that might be confused with other characters. If you think that this is intentional, you can safely ignore this warning. Use the Escape button to reveal them.
---
name: arc-open-work-register-the-single-verified-source-of-truth-post-stage-g
description: "Consolidated, code-verified list of what remains OPEN on ARC after Stage G was sealed (2026-06-10). Reconciles the scattered tracking surfaces — the chronological tracker, the ~10 standalone project-arc-* files, PENDING.md, the spec's Phase-2/held set, and content sweeps — against actual code/live state. Built 2026-06-11 because the records had drifted BOTH ways (real open work hidden; done work mislabeled \"pending\"). Supersedes the standalone \"-pending\" files for STATUS; those remain for detail. The chronological narrative stays in project-arc-rework.md; this carries current open-work truth."
metadata:
node_type: memory
type: project
permalink: claude-memory/project-arc-open-work-register
originSessionId: b85f1094-0658-47b4-a0ba-7a4323383aa9
modified: 2026-08-17T13:22:01.355Z
---
# ARC open-work register
**Single source of truth for what is OPEN on ARC.** Built 2026-06-11, ARC `main @ b220620`, live. Each item verified against code/live where marked **[verified]**; **[VERIFY]** = status uncertain, check before calling done. The rigorous spec↔code half is `/spec-code-audit`; this register also carries the content/governance/Phase-2 surfaces that audit does not.
> **Why this exists.** Stage G (sealed 2026-06-10) closed the *spec*, not ARC's *work*. Open items were scattered across the tracker, ten standalone `project-arc-*` files, PENDING.md, the spec's held set, and content sweeps in no spec. On 2026-06-11 several of those surfaces proved drifted in both directions (the AldineXXI selector index listed shipped features as "planned"; "pending" files described done work; real work sat unlisted). This register is the reckoning.
**Legend:** `[OPEN]` real remaining work · `[DEFERRED]` open by design, trigger-gated (Phase-2 / held / first-instance) · `[DONE—retire]` verified complete, the tracking file should be retired/archived · `[VERIFY]` needs a check.
---
## A — Open build work (the two undesigned-SVG-asset items the spec names but never realized)
- **A1. Vignette (F+1) — the big remaining build.** `[OPEN]` **[verified]** — 0 `.vignette` rules in compiled CSS, nothing rendered. Spec ready: `vignette-specification.md` (revised 2026-06-07, PENDING-31; build-time SVG+CSS renderer, Phase-α engine, zero-JS, AldineXXI §IX). Brief: `drafts/vignette-spec-revision-brief-2026-05-28.md`. The largest open build; the steward named it as "the big thing left."
- **A2. The cul-de-lampe — the designed Close ornament asset.** `[DONE 2026-06-17 — designed · first-instanced · rolled out to 7 essays · spec resolved]` — **the cul-de-lampe is live.** Confronted EB Garamond hederae (U+E001/E002, OFL), `.ornament.close`, **one text-em tall** (em-anchored, not constant — REVIEWED-42 consistency), `var(--fg)` opacity 0.7, CSS mask. Asset+rule+spec committed `d736df1`; rolled out (close on 7 essays; Vespers + Mushi-Ken reworked & **versioned**) in the follow-on commit. Close-only ruling: Essay/Hommage/Tombeau carry it; Fragment refused; Photo-essay declined; rest held-off (§IV *Which types carry the Close* + Sub-table 6, both reconciled). Placement = end of text proper, before Sources (apparatus spec). Publication mandate: every completed essay carries it. **The content half (B3) is now unblocked + started.** *Historical context (the long road to this) below:* — AldineXXI §IV names the *function* (Pause = rare within-piece breath, smaller scale; **Close = end-of-piece, the *punto finale*, full scale — "the visual signature of completion; *finis coronat opus*"**) but the **actual designed SVG cul-de-lampe is undetermined** — spec §IV *"Open question: the designed Pause/Close ornament itself"* **[OPEN — 2026-05-03]**, *"the asset itself is yet to be determined."* **[verified]**: compiled CSS still carries the *retired* classes (`.ornament.completion`, `.ornament.section`, `.ornament.chapter`, …) and has **no `.ornament.close`/`.ornament.pause`** — the asset was never designed, so the migration never ran (interim: the three-dot `.ornament` from the 06-07 hr doctrine stands in for Pause-at-threshold). Sibling to A1. Design sub-questions (one asset at two scales vs paired-distinct; motif lineage — Aldine cul-de-lampe vs Roman/Pompeian) in `project-arc-pause-close-ornament-and-hr-audit-pending`. The content half is **B3**. *(Caught by the steward 2026-06-11 — it was buried under the generic "ornament migration"; it deserves its own line as the crown of every finished piece.)*
## B — Open content sweeps (largely steward-owned, manual)
- **B1. Glimpse location + title cleanup.** `[OPEN — steward manual]` **[verified]** — steward does this by hand (2026-06-11). 193 live glimpses; **4 lack `location:` frontmatter**; titles need a cleanup pass. NB the glimpse *rendering* bugs (phone full-bleed, no-vessel) were fixed + deployed in Stage M — this is content/metadata, not code. Absorbs the residual of `project-arc-apparatus-refactor-todo` Tier 3 (EXIF/location for existing glimpses — now ~done).
- **B2. Threshold-`---` promotion walk.** `[OPEN — steward content track]` — apply the 2026-06-07 differentiated-hr doctrine across existing pieces: a bare `---` at a foreword→main-text *threshold* becomes `.ornament` (dots); `---` *within the body* stays silence. Doctrine + CSS settled (§IV amended, zero CSS change); the per-piece content walk remains.
- **B3. Ornament content migration (Option A) — the content half of A2.** `[OPEN — UNGATED 2026-06-17 when A2 landed; scope VERIFIED 2026-06-11]` — ⚠ *label corrected 2026-08-17: this read `gated on A2` for two months after A2 completed. A2's own entry had recorded "the content half (B3) is now unblocked + started" on 06-17 — so the fact was known and written, just never written **here**, which is where a reader checking B3's status looks. Kept as a marker of that failure mode rather than silently amended.* — steward ruled Option A (2026-05-03): once the cul-de-lampe asset exists (**A2**), migrate content off the retired-ornament classes onto the canonical Close/Pause, then retire the old SCSS. **Verified scope (sizable):** ~**95 content files** carry hand-authored `<div class="ornament …"></div>` — `completion` ×51 (= the Close / end-of-piece, the cul-de-lampe's job), `section` ×50, `thought` ×14, `chamber` ×12, `musical` ×7, `hermetic` ×5, `mathematical` ×2, … Several variants (`thought`, `mathematical`) aren't even in the current CSS → they already collapse to bare `.ornament`. All retired per §IV; all await the designed asset. Not negligible, and not runnable until A2. Files: `project-arc-ornament-spec-vs-content-mismatch-pending`, `project-arc-pause-close-ornament-and-hr-audit-pending`.
- **B4. Major content audit / archive of non-current files.** `[OPEN — was deferred]` — per ARC `CLAUDE.md` Known state: deferred until "the current version of the site is established; do not rearrange the content tree until that session." Stage G sealed arguably satisfies that condition now — candidate to schedule.
- **B5. Rethink the versioning links.** `[OPEN — design reconsideration; steward-raised 2026-06-17, NOT for now]` — the steward feels something "doesn't sit right" about the version-stamp links and couldn't yet name it. Current behaviour (verified in built HTML): the piece-end stamp reads *"Begun [place] **[origin-date→/v/]** · Revised [place] [revised-date, plain]"* — the **origin date is the only link**, leading to the prior version; the `/v/` page announces "You are reading a prior version… Read current →." Executor's candidate diagnoses (offered, not settled): **(1)** the cul-de-lampe (a *completion* seal, *finis coronat opus*) and the version link pull opposite ways — the close says *done*, the link a few lines below pulls *backward* into the superseded version; adding the close may have sharpened a latent tension. **(2)** "Begun [date]" frames the link as inception/seed, but the destination is a *complete prior essay*, not a beginning — label/destination mismatch. **(3)** for pieces revised by *subtraction* (Mushi-Ken's appendix, Vespers' loudness), the linked prior is the version the author *improved away from* — disclosing *that* a revision happened is integrity, but making the discarded version the foot-of-page reading-*destination* may overreach: provenance offered as invitation. Hunch: it's #1+#3 — ADR-005 designed versioning as a *record*, but rendered as a link it behaves like a parallel reading-path, and that sits oddly under a completion mark. Revisit when the steward can name it. (Grounds: ADR-005, essay-versioning-specification.md §3–4; the version-stamp builder in `site.hs`.)
## C — Deferred by design (Phase-2 / held — trigger-gated, NOT drift)
- **C1. Print/PDF posture + `arc-typography.sty` v0.3.** `[DEFERRED — Phase-2]` — build the Print/PDF LaTeX templates; update `tools/latex/arc-typography.sty` (v0.2, found stale vs current doctrine 2026-06-10) to current spec (posture-aware ragged/justified, Medium headings, 27.2rem measure, British quote-norm, xelatex glyph routing). Governs all future ARC PDFs. File: `project-arc-pdf-print-postures-session-plan`.
- **C2. OpenType feature catalogue (§I.i.j).** `[DEFERRED — Phase-2]` — feature→CSS mapping; the Stage-G audit (06-09) enumerated the set; the session opens against it. (`zero` absent from every EB Garamond face — recorded.)
- **C3. Held companions — Appendix D.** `[DEFERRED — Phase-2]` — Navigation Philosophy, Print Stylesheet, Footnotes — named, not drafted; reactive, no date.
- **C4. §VII.d Footnotes / Endnotes.** `[DEFERRED — first-instance]` — research/parked pending the first essay that needs the register.
- **C5. Held typographic options.** `[DEFERRED — held]` — justification (→ print spec), hanging-punctuation (→ browser Baseline), word-spacing (held at 0.20em default), reader font-size control (held; the banish-JS gate's one named exception).
- **C6. Tombeau route.** `[DEFERRED — first-instance]` — governed-but-unsurfaced; route + Compass slot emerge with the first Tombeau piece (non-convergence).
- **C7. Capsule apparatus.** `[DEFERRED — first-instance]` — deferred, not rejected; reopens when pedagogical-treatise content begins (§XII.e locks with first instance). File: `project-arc-capsule-apparatus-deferred-2026-05-05`.
- **C8. Per-piece epigraph chancery features; metric-matched font fallbacks.** `[DEFERRED]` — first-instance (epigraph chancery `swsh+init+fina`) / empirical SCSS-audit candidate (font-metric overrides).
## D — Governance debt
- **D1. Place outstanding REVIEWED entries.** `[OPEN — steward writes REVIEWED]` — PENDING-32 and PENDING-33 await REVIEWED placement; REVIEWED-36, 37, 38, 39, 40, 43 are drafted-for-placement (executed work, entries not yet placed). Constitutional: David/Claude.app write REVIEWED, not Claude Code.
## E — Stale "pending" files — verified DONE; retire or archive
- **E1. `project-arc-breadcrumb-spec-pending`** → `[DONE—retire]` **[verified]** — breadcrumb componentized + governed permanent sibling (2026-06-03); `.breadcrumb` lives in `_navigation.scss`.
- **E2. `project-arc-mimesis-acquisition-debt`** → `[DONE—archive]` — RESOLVED 2026-05-20 (stated in-file). Chamber-library import, not ARC-site work.
- **E3. `project-arc-404-page-design-pending`** → `[DONE—retire]` **[verified 2026-06-11]** — **the file predates the §VII.h spec and is stale.** Apparatus §VII.h (ADDED 2026-05-20) governs the 404; `content/404.md` + built `_site/404.html` **conform exactly**: `<title>Animal Rationis Capax</title>`, body "No text at this address.", real 404 via CloudFlare. Built and conformant, not "design pending." (Any future Close-ornament on it rides A2.)
- **E4. `project-arc-apparatus-refactor-todo-2026-05-06`** → `[DONE—retire]` — Tier 1/2 shipped (`e2fb14c`/`249475b`); Tier 3 glimpse location ~done (189/193) → residual in **B1**.
- **E5. `project-arc-spec-master-typographer-audit-pending`** → `[DONE—retire — superseded]` **[verified 2026-06-11]** — the masters-compliance pass was performed: `_audits/deep-typographic-audit-2026-06-09.md` exists (6-agent, masters folded), atop the 06-07 full bidirectional + 06-10 spec↔spec coherence audits. Retire unless a *specific* uncovered master-compliance dimension is named.
- **E6. `project-arc-web-typography-spec-coverage`** → `[DONE—retire]` **[verified 2026-06-11]** — Tier 1 all DONE (Lists/Code/Headings); Tier 2/3 DONE (Selection, Tables, Numerals, Smart-punct via §I.k). Only residual = the `<abbr>`/`<mark>` "styled-but-never-specced" corner; no ARC content meaningfully uses them — negligible, deferrable.
## G — Infrastructure / functionality / features (for a dedicated future ARC session)
**Session framing (steward, 2026-06-24):** when an ARC infrastructure/functionality/features session opens, **prioritize in-spec-but-not-built items first.** The **Vignette (A1)** is the flagship — in spec (§IX + `vignette-specification.md`, Phase-1-ready) yet zero built, no trigger gating it. **Open the session with a `/spec-code-audit` pass to census any *other* in-spec-but-non-existent items** so the priority list is concrete, not a hunch. The link-rot system (G1) is the first new-build candidate; the **Gwern.net deep audit (G3) is a companion track the steward wants to lead himself.**
- **G1. Link-rot prevention / link archival (Gwern borrowing).** `[PROPOSAL — noted 2026-06-24, not started]` — steward-raised on publishing *Two Notes* (its *fūrin* Wikipedia link reopened the thread). Adopt a *proportionate* version of Gwern's link-preservation discipline for ARC's external citations. **Three rungs:** (0) *detect* — `make linkcheck` (e.g. `lychee`) over the corpus → dead/redirected-link report, optionally scheduled; (1) *archive-on-publish* — submit each external link to the Internet Archive Save-Page-Now (+ archive.today), record `url → {snapshot, date}` in a sidecar `data/link-archive.yml`; (2) *self-host + fallback render* — local SingleFile snapshots + a template/apparatus offering the archived copy (auto-swap on 404). **Governed, not in-stride (steward-flagged):** Rung 2 touches **`site.hs`** (the carefully-rewritten Stage-G routing/contexts — §1 protected surface) and the **sealed AldineXXI spec** (how an archived-link fallback *renders* is a typographic/apparatus decision → jurist territory), plus new build infra; Rungs 0–1 are lower-risk (script + data file) but still warrant the loop given reach. **Path:** `[PROPOSAL]` in PENDING.md → jurist on the rendering/apparatus question → phased build (0→1 first; 2 a considered decision — ARC's small scale may make a full self-hosted mirror disproportionate). **Ethos:** link-permanence = the prime directive applied to citations (*build what you will not need to rebuild*; a corpus inheritable by Lune & Kai without dead links).
- **G2. Zero-JS reading-progress bar (Gwern-occasioned).** `[CANDIDATE — borderline-loud, undecided; needs steward judgment first]` — Gwern's bottom running-head/progress bar is pure JS (declined under banish-JS, REVIEWED-32). A zero-JS `animation-timeline: scroll(root)` progress bar was flagged 06-22 as an iPhone test candidate (different/simpler than the §VII.f `view()` reveal, which won't drive on iOS for a fixed consumer). **Caveat:** an always-on progress indicator is *visible chrome* — it may not survive ARC's quiet-over-loud filter; decide whether it's wanted at all before building. If yes, a ~10-line CSS test → load on a real iPhone. (Was ledger-only 06-22/06-23; promoted here so it perdures.)
- **G3. Deep audit of Gwern.net (steward wants to lead).** `[OPEN — steward-initiated]` — a deliberate harvest pass over gwern.net through the recorded filter: *adopt the invisible durability craft (build-time, provenance, permanence); decline the visible density (popups, JS progress, similar-links clutter, link-dense ToC).* Probe candidates worth a proportionate ARC version: integrity hashes on archived snapshots, build-time link-checking (folds into G1), quiet backlinks, content-addressing / perdurance patterns — and explicitly catalogue what to **decline**. Output: register entries surfaced for steward decision, not a fait accompli. Shared nerve with Gwern = the *intent to perdure* (he loudly, ARC quietly), not his density.
## F — The chronological tracker
`project-arc-rework.md` is the **narrative** record, true through **2026-06-07 evening** (last entry: the pre-3R Fowler note). It is owed compact appends for **06-08 → 06-11**: W3R re-partition close + deploy; Wave 5 + measure→72ch + soft rag; **Stage G CLOSED + reconciled + SEALED + GPG-signed** (06-10); **§VII.f running head + W1.15 compass presence-reveal** shipped (06-11). The tracker's "CANONICAL STAGE STATUS" line (≈L3852, "as of 2026-06-05") is stale. **This register now carries current open-work truth; the tracker carries the story.** Tracker annotated to point here (2026-06-11).
---
*Maintenance: update this register as items close; move `[DONE—retire]` files to an archive; promote `[VERIFY]` to a verdict once checked. Canonical current-state for ARC open work lives HERE — not in the scattered files, and not inferred from "Stage G is done."*